Milestones
List view
Five milestones and a release. Effort legend S 6h, M 24h, L 60h: M83 M, M82 M, M81 L, M80 L, M84 L, and the 2.6.0 release S, so 234 hours, about seven weeks. Due 11 September 2028, computed at 60 hours a week from 15 August 2028, after the products ahead of it in the order of the boards. It carries an open question the dating does not answer: whether the release is 2.6.0 or 3.0.
Due by September 11, 2028•0/6 issues closedSix milestones and a release. Effort legend S 6h, M 24h, L 60h: M74 L, M75 M, M76 M, M77 M, M78 S, M79 L, and the 2.5.0 release S, so 204 hours, about six weeks at the rate this board has held while a tier is in flight. Due 15 August 2028, computed at 60 hours a week from 21 July 2028, after the products ahead of it in the order of the boards.
Due by August 15, 2028•0/7 issues closed